Rcdh of Pennsylvania INC has been paid $89,750 by the State of Delaware since FY2018, primarily through Dept of Transportation's Capital Project Cost Center division.
| Program | Agency | Amount | Years |
|---|---|---|---|
| Capital Project Cost Center | Dept of Transportation | $89,750 | FY18–FY20 |
| Fiscal year | Total | Checks |
|---|---|---|
| FY18 | $68,750 | 27 |
| FY19 | $12,500 | 2 |
| FY20 | $8,500 | 2 |
| Date | Department | Category | Amount |
|---|---|---|---|
| Oct 18, 2019 | Dept of Transportation | Settlement Costs | $5,000 |
| Sep 23, 2019 | Dept of Transportation | Settlement Costs | $3,500 |
| May 31, 2019 | Dept of Transportation | Settlement Costs | $10,000 |
| Sep 20, 2018 | Dept of Transportation | Settlement Costs | $2,500 |
| Jun 7, 2018 | Dept of Transportation | Settlement Costs | $2,400 |
| Jun 7, 2018 | Dept of Transportation | Settlement Costs | $600 |
| May 17, 2018 | Dept of Transportation | Settlement Costs | $2,500 |
| May 1, 2018 | Dept of Transportation | Settlement Costs | $5,000 |
| Mar 15, 2018 | Dept of Transportation | Settlement Costs | $2,500 |
| Mar 15, 2018 | Dept of Transportation | Settlement Costs | $2,500 |
| Mar 15, 2018 | Dept of Transportation | Settlement Costs | $2,500 |
| Mar 15, 2018 | Dept of Transportation | Settlement Costs | $2,500 |
| Mar 15, 2018 | Dept of Transportation | Settlement Costs | $2,500 |
| Mar 15, 2018 | Dept of Transportation | Settlement Costs | $2,500 |
| Feb 8, 2018 | Dept of Transportation | Settlement Costs | $2,000 |
Source: State of Delaware checkbook · synced 2026-07-25. Open source dataset ↗