… midst of their interior fit-outs. The exterior shells of these buildings are fully watertight, representing a big milestone for the project. Interior framing has been completed across all three spaces, and mechanical, electrical, and p …
Open p.81 ↗… $0.00 Cumulative Expenditure $4,000,000.00 Throughout the month of April, the project achieved several critical milestones. The slab-on-grade placements were substantially completed, with the exception of the gymnasium slab, which is …
Open p.172 ↗… alf of the ELA area. The final slab-on-grade pour (excluding the gymnasium) is scheduled for early May. A major milestone was reached at the end of April with the commencement of steel erection on April 29. This work will continue into …
Open p.173 ↗… ay and June marked the vertical progression of the project, as steel erection gained momentum. This significant milestone supports the advancement into the next phase of construction — building the exterior envelope. Behind the scene …